Gross Margin of 70%, Yet Still Short on Cash? The Second Half of AI Infrastructure: From Competing on Scale to Competing on Delivery

11/24 2026 576

Two pieces of news over the past two days have laid out, on the same page, the most unvarnished account book of AI infrastructure.

On one side are supply and demand data disclosed by Keras founder François Chollet: HBM and DRAM capacity scheduling has been locked through 2029, GPU spot prices are still climbing, frontier training compute is roughly doubling every five months, and the profit margin of the AI inference business runs as high as 70%–85%.

On the other side is a warning from Musk: next year's funding shortfall will be very severe. There is a time lag between compute delivery and stable go-live, and the AI industry may face a working capital shortage on the order of hundreds of billions of dollars next year. Even a misalignment of just a few months is enough to swallow enormous cash flow.

Set these two pieces of information alongside the 2026 third-quarter reports just disclosed by the tech giants, and a not-so-reassuring conclusion surfaces: demand for compute has not been disproven—unit gross margins are even astonishingly high—but the cash flow timeline is about to become unsustainable.

So, with gross margins so high, why is there not enough money? Who in the industrial chain is being revalued? And what should we really be watching in the second half?

1. "Fire and Ice" in the Financial Reports: Cloud Revenue Is Rising, Cash Flow Is Shrinking

Start with the 2026 third-quarter reports and full-year capital expenditure guidance of the four major tech giants (Microsoft, Alphabet, Amazon, Meta). The most glaring issue is not slowing business, but the increasingly narrow safety buffer between operating cash flow and capital expenditure.

In the third quarter of 2026, the four companies' combined quarterly capital expenditure reached $201.9 billion, more than doubling year-on-year—equivalent to burning about $2.2 billion per day. Their combined full-year guidance jumped to $720–745 billion.

Meta: quarterly capital expenditure (including finance leases) reached $34.9 billion, already exceeding operating cash flow of $32.8 billion for the same period, and quarterly free cash flow turned to $2.1 billion. The full-year capital expenditure guidance falls in the high range of $135–145 billion. Within nine months, the scale of fixed assets grew by more than 40%, and depreciation began to wash through the income statement ahead of schedule, forcing the company to replenish its ammunition through equity financing and bond issuance.

Microsoft: Azure grew by more than 40% year-on-year in the third quarter, and commercial remaining performance obligations (backlog orders) climbed to $678 billion, but management clearly warned that computing supply remains constrained, with full-year capital expenditure maintained at around $175 billion.

Alphabet: Google Cloud's quarterly revenue grew 82% year-on-year, and operating profit more than tripled, indirectly confirming the earnings explosive power of large-scale inference; but full-year capital expenditure of $195–205 billion likewise sharply compressed free cash flow, and the company turned to the European bond market for debt financing.

Amazon: AWS has maintained accelerated growth for several consecutive quarters, backlog orders are approaching $500 billion, and the full-year capital expenditure expectation was raised to about $220 billion, with the reason stated quite plainly—"higher memory and hardware costs."

On the income statement, operating margins and cloud growth remain beautiful; on the cash flow statement, front-loaded capital expenditure is pumping the water dry, with the depreciation curve chasing revenue from behind. This is the first layer of contradiction in this article: the business is making money, but cash is getting tighter.

2. Orders Locked Through 2029: The Bottleneck Has Long Shifted from "Chip Design" to "Memory and Delivery"

Now look at the supply side. The data set disclosed by François Chollet points clearly to one thing: HBM and DRAM capacity scheduling is locked through 2029, and the memory shortage may even extend into the 2030s. He himself takes a cautious attitude toward the path of large language models to general intelligence, but on the supply-demand judgment for physical compute and high-bandwidth memory he is quite direct—model routes can be debated, but rigid demand is still moving upward.

This brings two consequences.

First, the "compute content" of capital expenditure is being diluted by upstream premiums. Scheduling locked through 2029 means upstream memory and core hardware hold extremely strong pricing power. That line in Amazon's financial report—"higher memory and hardware costs"—is exactly where this pricing power lands on the statements: the money has been spent, but it will not linearly turn into an equivalent proportion of usable racks.

Second, the bottleneck has shifted from tape-out to physical delivery. Goldman Sachs estimates that global AI capital expenditure in 2026 will approach $1 trillion, with cumulative related debt issuance of about $600 billion. At this scale, what really blocks racks from going live is HBM and advanced packaging scheduling, grid connection, high-density liquid cooling retrofit, and stable tuning of large-scale clusters. The more expensive the hardware and the higher the power density, the longer every step takes from confirmed cash outflow in the financial statements to racks actually being powered and generating revenue.

3. A 70%–85% Inference Gross Margin Is Only a Ticket to Entry

The "70%–85% profit margin in the inference business" disclosed by François Chollet is the hardest confidence currently supporting the entire AI infrastructure investment narrative, and it is also indirectly confirmed by the jump in operating margins at AWS and Google Cloud. As long as models enter high-frequency invocation and large-scale inference, the marginal account can be made to work; with the volume ramp of agents, multimodality, and long-context workloads, every generational leap of models is pushing invocation volume up geometrically.

But from a business and financial perspective, an inference gross margin above 70% is a ticket to entry, not the finish line.

What Musk calls the "hundreds-of-billions-of-dollars funding gap" is essentially the working capital mismatch unfolding in giant companies' financial reports, and it can be broken down into three layers.

The second layer, inflows are back-loaded and blocked: chips arriving does not equal the ability to make money. As long as grid interconnection, liquid cooling tuning, or cluster rack installation is delayed by two or three months, the racks cannot go live, and revenue is zero.

The third layer, leverage amplifies the cost of time: at the scale of trillion-level capital expenditure and hundreds of billions of dollars of debt financing, interest is calculated by the day, and equipment depreciation is accrued by period. Even if the entire industry's delivery cycle is lengthened by only one quarter overall, the capital occupied and financing costs sunk in semi-finished projects will rapidly expand into a gap on the scale of hundreds of billions of dollars. Musk even said bluntly that in the future data center sector, more than 200 companies may face acquisition or bankruptcy.

In one sentence: gross margin is unit economics, cash flow is time economics. The former determines whether it is worth doing; the latter determines whether you can survive to finish the job.

4. The Delivery "Scissors Gap" Is Dividing the Industrial Chain

As the third-quarter reports begin to expose the scissors gap between "high capital expenditure and delivery lag," the valuation logic of the capital market for the four core links of the industrial chain is diverging sharply—shifting from "competing on scale" to "competing on delivery certainty and capital turnover efficiency."

Industrial chain link

Core financial and operational risks

Direction of valuation re-rating

Hyperscale cloud providers

Capital expenditure is approaching or even temporarily exceeding operating cash flow, new depreciation is beginning to materialize, and part of spending is being absorbed by memory premiums

From simply rewarding "surges in capital expenditure" to closely watching free cash flow coverage, backlog order conversion speed, and return on invested capital

Compute leasing providers (emerging compute clouds)

High-leverage financing to buy cards and build data centers, zero tolerance for delivery delays; delay means "paying interest and depreciation first, collecting rent later"

Players bound to top-tier giants through long-term irrevocable agreements gain certainty premiums; small and medium-sized lessors lacking order moats are being accelerated out

Memory manufacturers (HBM/DRAM)

Scheduling locked through 2029, with extremely strong earnings visibility and pricing power; but must guard against downstream funding tightness causing slight adjustments to forward pacing

From strong-cycle discount to re-rating based on long-term agreement visibility, playing the most stable profit-retaining "rent collector" in the compute infrastructure cycle

System integrators and infrastructure supporting providers

Project delays directly trigger longer advance funding and default risks; the technical threshold for high-density liquid cooling and power supply retrofit rises sharply

Players who can help customers shorten delivery cycles by 3–6 months gain scarce premiums, re-rated from low-valuation contractors to high-stickiness infrastructure partners

From this table, memory manufacturers are the most stable "rent collectors" in this round, with scheduling locked through 2029, extremely strong earnings visibility and pricing power, and a valuation logic that has shifted from strong-cycle discount to re-rating based on long-term agreement visibility. Compute leasing providers bound to top-tier giants through long-term irrevocable agreements obtain certainty premiums, while small and medium-sized players lacking order moats are being accelerated out. System integrators and infrastructure supporting providers that can compress delivery cycles by 3–6 months are being re-rated from low-valuation contractors to high-stickiness infrastructure partners.

The pressure falls on both ends: one end is emerging compute clouds that rely on high leverage to buy cards and build data centers and have zero tolerance for delays—a one-day delay means "paying interest and depreciation first, collecting rent later"; the other end is the giants themselves, whose capital expenditure temporarily exceeds operating cash flow and who can only sustain themselves through bond issuance and equity financing.

5. Three Indicators to Watch in the Second Half

HBM scheduling locked through 2029, an inference gross margin of 70%–85%, and the latest financial reports of cloud giants jointly prove that AI infrastructure is not a castle in the air.

But sharply narrowing free cash flow and Musk's warning about a hundreds-of-billions-of-dollars gap pull the industry back to the coldest business common sense: compute infrastructure has never monetized linearly along the ideal curve in a business plan. Engineering delivery speed and cash flow endurance are the hard indicators that determine who can make it to the end.

Therefore, what is truly worth watching in the second half is not "how much larger the clusters should be built," but three indicators that can be verified quarter by quarter.

First, the coverage ratio of cash flow to capital expenditure: it determines whether a manufacturer's expansion is "self-sustainable" or "debt-fed."

Second, the conversion speed of backlog orders: no matter how high backlog orders (RPO) are, if they cannot be converted into revenue on schedule, they are just a pretty IOU.

Third, depreciation as a share of revenue and the pace of rack installation: the former shows how fast the income statement is being eroded, while the latter shows the real capacity of "non-chip" links such as power, liquid cooling, and cluster tuning.

As AI infrastructure enters the second half, simply shouting "build larger clusters" is no longer enough. Whoever can faster convert capital expenditure into stable compute that goes live on schedule, and whoever can squeeze out higher full-lifecycle energy efficiency and total cost of ownership (TCO) advantages through high-density liquid cooling and memory scheduling, will truly keep the high gross margin of inference in their own pocket.